Case Study
Cost Savings Through Alternate Foundation Design
PROJECT PROFILE D’Appolonia was engaged to prepare foundation recommendations for a new $125 million chemical plant planned for a site near the Mississippi River. Sub- surface soils at the site consisted of relatively soft, compressible clay. The primary plant facilities include four movement-sensitive process structures and 14 storage tanks. A geotechnical report prepared by a local firm recommended placing all structures on pile