Case Study
Construction Of Household Waste Recycling Centre Ellmesre Port, Cheshire
CONSTRUCTION OF HOUSEHOLD WASTE RECYCLING CENTRE ELLMESRE PORT, CHESHIRE Importation of 20,000 cubic metres of surcharge fill to compress the peat underlying the site. The fill was left in place to allow settlement over 6 months. Following the confirmation of sufficient compaction half the fill was then removed and used in landscaping bunds and the works constructed on the remaining material. The construction of the waste site was undert