Case Study

Consolidation Of Mineral Workings And Bearing Piles

Consolidation Of Mineral Workings And Bearing Piles

Pages 2 Pages

www.technikgs.com Case study LOCATION REQUIREMENT TECHNIQUES MAIN CONTRACTOR Project Overview Technik Ground Solutions (TGS) normally operates as a specialist geotechnical sub-contractor but has recently completed a five month project acting as the Principal Contractor for a world’s leading chemical company. On this project a 35 metre by 25 metre building, within the existing plant required to be adapted; extended vertically by two storeys to accommodate new much heavier sensitive processing machinery. TGS were responsible for the geotechnical design and the project focused on achieving a fast-track programme with the most cost effective solution. Technical and financial feasibility advice was provided well in advance of the project commencement on site. TGS were respo