Case Study
Combined Heat Hospital In The North West Of England
The project comprised of the installation and setting to work of a Combined Heat and Power Plant at a large teaching hospital in the North West of England. The new 1800kw gas fired engine, housed within a purpose built acoustic enclosure, generates 2.5MVA 400V/6.6kV of power to supplement the existing hospital HV Ring Main. A new waste heat boiler was installed within the existing boiler house to utilise the heat generated by the flue gasses off