Case Study
Coffee Processing Facility Vermont - Packaging Line Isolation
Hallam-ICS - F&B - 3 CASE STUDY Coffee Processing Facility Vermont Packaging Line Isolation The company’s product development roadmap required a fast-track design/build instal- lation of an enclosure to surround an existing pack- aging machine in their facility operating under GMP rules. Our client had a 5 week window to deliver the completed project to meet these environmental requirements: ? Provide a 10% relative humidity and 75 degree Fahre