Case Study Cleator Moor – 10MW battery storage project CLIENT: Low Carbon Storage Investment Company Ltd LOCATION: Cleator Moor , Cumbria DURATION: 12 months A 10MW battery system providing services to help balance the national grid using its high-speed response times to the electrical grid network. Details Prospus Group were appointed as the developer for Low Carbon Ltd. on the pre-development works for the site. Our work included: • Securing the site and negotiation the Heads of Terms, Option and Lease agreement • Securing access to the site over 3rd party land • Securing the grid connection for the project and project managing the negotiations with the district network operator • Developing the planning strategy for the site • Developing and submitting the planning applicati