Civil Construction State Road 60, Vero Beach Handex roadway crews pushed 8 sections of ADS N-12 poly piping through the casing to the next structure in less than 12 hours. The Challenge Install 860’ LF of stormwater piping through environmentally impacted areas along a major thoroughfare and hurricane evacuation route for Florida Department of Transportation, District 4. The Issues • The stormwater piping must be lined to prevent impacted groundwater from entering thestormwater system and water shed areas. • Install piping across roadways in 24 hours without closing roadways. • No disruptions to operating businesses or impacts to neighboring residences. • Keep existing stormwater system fully operational until new system is online. The Solution Our experienced Heavy Construction Team analy