Design-Build Turnpike Service Plaza Handex installed an extensive Air Sparge / Soil Vapor Extraction (AS/SVE) system within a 6-month time-frame The Challenge Florida’s Turnpike Enterprise Authority had a release from the previous underground storage tanks at the Canoe Creek Service Plaza in St. Cloud, Florida. The Solution We were hired to complete the remediation of a very large gasoline impacted area at the site. We designed and implemented the solution for Florida’s Turnpike Enterprise. Construction plans, including recovery system layout, trenching details, well design and underground piping, were submitted to obtain FDOT right-of-way (R-O-W) and Osceola County Building Departmentpermits to begin the construction. Utility clearance was also required for the facility prior to undergrou