Chemical Plant, Lancashire
CASE STUDY 01484 715400 info@accflooring.co.uk www.accflooring.co.uk Unit 1a Woodvale Workshop, Thornhill Beck Lane, Brighouse, West Yorkshire, HD6 4AH. Chemical Plant, Lancashire A long standing client of ACC Flooring asked if we could refurnish two external bunds whilst their plant was on shutdown. The two bunds were side by side but both were in need of extensive work not only to the floor areas but also around the tanks and to the plinths. To one of the bunds, a crack had appeared in the floor which has run through the brickwork to the bund wall causing loss of containment. Due to the chemicals which were to be stored in the bunds a standard high build coating or chemical resistant coating would not give sufficient protection. The existing