Case Study
Chemical Bund, Lancashire
CASE STUDY 01484 715400 info@accflooring.co.uk www.accflooring.co.uk Unit 1a Woodvale Workshop, Thornhill Beck Lane, Brighouse, West Yorkshire, HD6 4AH. Chemical Bund, Lancashire ACC Flooring was asked by a long standing client in the chemical industry to solve a problem with an external chemical bund which contained acid and alkaline. The existing resin floor finish had failed and in addition rainwater was pooling in several areas. There were also unprotected plinths which required dressing. A large tank wall was also showing signs of protection deterioration. The failed resin floor finish was uplifted by using kango’s to expose the concrete substrate which was then mechanically prepared with vacuum enclosed diamond grinders. A laser level wa