Case Study
Cheese Manufacturing Plant - The existing masonry production area walls (500m²) required a complete re-coat without any disruption
Cheese Manufacturing Plant - The existing masonry production area walls (500m²) required a complete re-coat without any disruption
Overview The existing masonry production area walls (500m2) required a complete re-coat without any disruption to other areas of the plant. It also had to be carried out in a very tight timescale and have no odours. The surface finish had to be easy to wash and decontaminate seamless with food contact approval. Challenge Working in a very restrictive area, limited timescale, minimal surface preparation, FDA approval, odourless product, combined with temperature variations added to the difficulty of the project. Solution Two coats of Chemco Epo-chemTM RA 500M solvent-free, wet tolerant glassflake epoxy system @ 200µ per coat applied by brush and roller. Outcome The work was carried out on time, with no delays to the program and no impact on other