Case Study
Beechwood Independent Schools
Beechwood Independent Schools 54 Beechwood Rd Fort Mitchell, KY 41017 Project Type: Energy Savings Project Impact: Better performing systems and savings in ex- cess of $75,000 per year. Project Reference Methods Employed: $747,579 Energy Saving Project to upgrade aging facility infrastructure. Background : The school board was dealing with aging facilities and increasing utility costs. The school district has one main school building for the High School, Middle School and Elementary School. This building was added onto many times over the years and some sections were nearly 100 years old. The problem was that each addition has its own set of mechanical equipment. Often, architects and engineers do not expend the extra ef -fort to determine if over-sized equipment fr