Aqua Dam 10' - Mirimichi Golf Course LOCATION: Millington, TN TIMEFRAME: May 7th-May 12th 2011 SCOPE OF WORK: Provide 600 LF of 10’ high Aqua Dam and Supervision to install. PROJECT PARTNERS Owner: Mirimichi Golf Course Client: Justin Timberlake Installation: Layfield Environmental Material Supplier: Aqua Dam Inc Challenge Challenge was to meet client deadline and expectations. Order was placed on Thursday 10 am, Aqua dam was fabricated by Friday at 2 pm and shipped by 7pm. Aqua dam was on site by 2 am Monday morning. Severe weather such as Tornado warnings, lightening and thunderstorms had to be overcome during transportation & installation. One of the Aqua dams was suspended in a steel plate that broke loose and caused delays in unloading. Launching berms were not high and wide enoug