Case Study

Andeavor hired POWER to study its facility then design and implement a plan to bolster reliability of the century-old facility

Andeavor hired POWER to study its facility then design and implement a plan to bolster reliability of the century-old facility

Pages 2 Pages

Accomplishments Client: Andeavor Location: Utah After a series of expensive power outages at its Salt Lake City refinery, Andeavor hired POWER to study its facility then design and implement a plan to bolster reliability of the century-old facility. The ultimate goal included the ability to island the refinery from the utility grid without disruption. The refinery’s electrical system relied on a single overhead 46 kV line to distribute power to the multiple load centers, which included two cogeneration units connected to the same bus. During the study, the refinery was contemplating several new electrical load additions to manage a heavier crude oil. POWER recommended a fully redundant and growth flexible electrical system, including two feeders for every load distribution center. The proj

Join for free to read