Case Study
Aligned Energy
Aligned Energy | HKS Architects The Challenge Aligned Energy purchased a vacant, 300,000-square foot semi-conductor facility in West Jordan, Utah, in January 2018 with a commitment to have its first data center client operational by August 2018. The building was constructed in the late 70s under significantly different building codes and had been empty for more than five years. The Design Solution HKS provided architectural upgrades to the building’s entrance, interiors and exterior security. We provided a locally-based team that could respond to the site immediately when walls were demolished, and unforeseen conditions discovered. When problems arose, the team could react quickly to find solutions and keep the project on schedule. Telecom services are provided through multiple carriers an