ABB managed the remediation of a former Petrol Filling Station (PFS) situated above a sensitive principal chalk aquifer

ABB managed the remediation of a former Petrol Filling Station (PFS) situated above a sensitive principal chalk aquifer

Pages 2 Pages

— OIL AND CASE STUDY - MAJOR OIL AND GAS PRODUCER, SOUTH WEST ENGLAND PFS in-situ remediation ABB managed the remediation of a former Petrol Filling Station (PFS) situated above a sensitive principal chalk aquifer. The site was closed due to a Compulsory Purchase Order (CPO) associated with a road widening scheme. Following site demolition, an environmental site investigation revealed hydrocarbon contamination in the chalk aquifer. A remedial solution therefore needed to be implemented at the site to address the identified impacts and associated potential environmental liabilities. Whilst being undertaken as voluntary remediation work, given the environmental sensitivity of the site, the client required that the remedial solution be agreed with the regulator. The remediation

Join for free to read