A38 Dobwalls Bypass ECI

A38 Dobwalls Bypass ECI

Pages 3 Pages

A38 Dobwalls Bypass ECI The project was combined with the A30 Merrymeet ECI, and these were managed as a single package to maximise efficiency and economies of scale. The scheme was procured though the Early Contractor Involvement (ECI) procedure, which has resulted in time savings and improved value to the Highways Agency. Construction commenced in February 2007 and was completed two months ahead of schedule in April 2009. Main project features The mainline A38 comprised 3.2km of dual two lane all-propose carriageway The new A390 Link Road, the Moorswater Collector Distributor Road and other amendments to the local roads total 5km of single carriageway A roundabout at the junction of the A38 and A390 Composite over bridges at Havett Road and Looe Mills Junction A pre-cast concrete arch st