Case Study
A Major Diamond Miner Eliminated 53 Out Of 88 Confined Space Events Per Chute By Changing To Laminite Skirt Board Liners
A Major Diamond Miner Eliminated 53 Out Of 88 Confined Space Events Per Chute By Changing To Laminite Skirt Board Liners
• Replace Overlay plate with Laminite ® Skirt Board Liners. • Laminite ® Skirt Board Liners lasted 10 weeks. • Plant down time for wear plate change out is now 35 days per annum. OUR SOLUTION CHALLENGES THEY WERE FACING LAMINITE ® SKIRT LINERS VS OVERLAY PLATE MINING MASSIVE SAVINGS A MAJOR W.A. DIAMOND MINER ELIMINATED 53 OUT OF 88 CONFINED SPACE EVENTS PER CHUTE BY CHANGING TO LAMINITE ® SKIRT BOARD LINERS • Maintenance costs and downtime - wear plant change out is 88 days per annum - overlay plates only lasting 4 weeks. • Eliminate confined space work. • Reduce maintenance on a Skirt Board conveyor section from chute discharge. Laminite ® wear plates installed where overlay plates were Same Laminite ® wear plates 10 weeks later Overlay liner wear plates at installation