3D-P Demonstrates Immediate Production Improvement through Real Time Data Collection
A production study performed in March 2017 at a medium size mine in the Eastern Goldfields, Western Australia demonstrated that a 10% production improvement could be immediately achieved though the implementation of 3D-P Production System, powered by iVolve, on their excavators and trucks. 3D-P Demonstrates Immediate Production Improvement through Real Time Data Collection USA | Canada | South America | Australia Visit www.3d-p.com To learn more, call 3D-P at + 1.403.203.3018 CASE STUDY Excavator Efficiency: Reported Problems 1. Large spread in the number of buckets used during a load cycle, affecting predictability and truck waiting time. 2. Considerable variation in swing speeds, affecting predictability and truck waiting time. 3. While the study was performed, an overload