Case Study
227-233 Tottenham Court Road
It is an amazing achievement to have completed such a complicated enabling works and demolition phase on programme. Their efforts set this project off to a good start. Paul Middleton, Project Manager, Costain A former grand retail and office building dating back to end of the 19th Century needed to be demolished to redevelop the site into a prestigious retail and office complex. Being located in a 'conservation area, the buildings extensive ornate' terracotta façade was to be re- tained. A scheme was developed, where the façade was supported using a combination of part external temporary steel support and by installing the new steel frame within the structure, with modifications to support the structure in the temporary case during demolition. This ensured the busy thoroughfare of Tottenha