i1: TE - . LTD IN 2007 TEl were awarded the contract to re-tube TAl condenser at Wylfa Nuclear Power Station in Anglesey North Wales. This is the largest of its nuclear type in the UK. This contract was successfully completed on schedule and to the clients satisfaction in SEPTEMBER 2007. The condenser is divided into six banks of tubes at two levels. In total 42000 tubes at 1" OD with an effective length of 25 feet 11 inches. The tubes are sealed