Case Study

Wellcom™ System - Multiphase Boosting (Deferring installation of Multiphase Pump)

Wellcom™ System - Multiphase Boosting (Deferring installation of Multiphase Pump)

Pages 1 Pages

www.caltec.com Wellcom™ System - Multiphase Boosting (Deferring installation of Multiphase Pump) Onshore – Middle East Issue • LP oil well often shut-in/ struggling to flow Solution • Multiphase HP well used to kick off and reduce back-pressure of LP well using Caltec’s Wellcom skid Benefits • Used available energy otherwise lost in choke from HP well 40 psi pressure drop for LP well • Improved flow regime in well bore, resulting

Join for free to read