Case Study

Vincent Square, Westminster

Vincent Square, Westminster

Pages 1 Pages

Customer Fairpoint Properties Main Contractor J Reddington Ltd Date 2005 Commitment Innovation Sustainability Case Study MGF designed a scheme suitable for the complex construction sequence using a mixture of modular 120Te hydraulic and mechanical cross struts spanning up to 23m across the capping beam. Where other spans were too great, 54Te mechanical struts were utilised as raking struts, and knee braces were used in the corners of th

Join for free to read