Case Study
Victoria and Albert Museum
Victoria and Albert Museum www.integral.co.uk ArtsCase Study Victoria and Albert Museum Medieval & Renaissance Galleries Refurbishment The Project involved the refurbishment of 10 existing galleries and the formation of a new ‘Daylit Gallery’ from previous roof plant area. This was a full M&E package of Heating, Ventilation and Electrical. Contract worked on CDP (Contractors Design Proposals), which as difficulties arose the contractor was to seek the best possible solution to maintain program timescales. Each phased completion achieved, despite building work problems and Grade 1 Listed Building limitations. Variations agreed as the contract went on and final account was within contract constraints. Each section completion was followed by a Curators fit out ready for opening. Cl