UPS built a facility to store and distribute pharmaceutical products that have rigorous temperature requirements

UPS built a facility to store and distribute pharmaceutical products that have rigorous temperature requirements

4790 West 73 rd Street I Indianapolis, Indiana 46268 Phone: 317-290-8500 I Fax: 317-290-1900 www.aesrack.com Project Identification Customer: UPS-SCS (Pharmaceutical Logistic) Location: Louisville, Kentucky Design Specifications Facility Warehouse 297,000’ x 32’ High Winter Operation 70 ° – 0 ° Summer Operation – 70 °- 95 ° Case Study Report Air Energy Systems, Inc. Bill Maher bmaher@aesrack.com Project Challenge: UPS built a facility to store and distribute pharmaceutical products that have rigorous temperature requirements generated and upheld by the FDA. The FDA requires no more than a +/- 2 ° F temperature difference anywhere in the facility; redundancy is also required as products are rendered unusable if