Underground Cable Link, 132 kV and 11 kV Ma Wan & Kap Shui Mun Cables Channel Crossing
Underground Cable Link 132 kV and 11 kV Ma Wan & Kap Shui Mun Cables Channel Crossing Cable data Project content Voltage 132 kV, 11 kV AC XLPE cables, joints and terminations Power 155 MVA, 7 MVA Optical fibres Length 22 000 m, 13 000 m Cable system design Conductor 1000 mm 2 , 3x400 mm 2 Cu DTS equipment Insulation XLPE Installation and testing Weight 20 kg/m, 22 kg/m Customer Skanska Civil Engineering AB in Hong Kong Year 2000BU Cables Teleph