UltraFab Meets Zero Emissions Gas Treatment Limit

UltraFab Meets Zero Emissions Gas Treatment Limit

Pages 2 Pages

ecolab.com/ultrafab CASE HISTORY CH-0174 UL TRAF AB TM MEETS ZERO EMISSIONS GAS TREA TMENT LIMIT SITUATION An extensive drilling program was underway in northwestern Canada and considerable gas production was anticipated from the area. A multi-phase amine facility was being built to ultimately process 1.6 Bscf/D (45,300 e3m3) of gas. Each phase of construction included two amine facilities, each with a capacity of 200 MMscf/D (5,600 e3m3). Four phases or more were anticipated. CHALLENGE Gas flowing into the amine facility was expected to contain up to 12% CO 2, resulting in a relatively large acid gas stream. To treat the acid gas stream, each amine train was designed to be directly followed by a four-train acid gas sweetening unit (AGSU) with each AGSU capable of treating app