Former Goods Distribution and Maintenance Depot CASE STUDY TURNKEY, DESIGN AND BUILD BIOREMEDIATION £240,000 PROJECT VALUE: PROJECT TIMESCALES: 18 months CHALLENGE: This former goods distribution and HGV maintenance depot had discrete areas of hydrocarbon impact associated with fuelling and maintenance activities. The client required a turn-key service to design and deliver a voluntary remediation scheme to protect the Water Environment and manage liability. REMEDIAL METHODOLOGY: ERS was appointed as Principal Contractor to deliver a turn-key remediation service at this former distribution depot with discrete areas of impact by middle and heavy range hydrocarbons. Building & Workspace Solutions Ltd were the CDM Co-ordinator. An outline remediation strategy had been prepared by