Turbocaser Express™ 7” - Second Deployment Offshore Norway Delights Client on Challenging Run by Getting 7” Liner to TD at First Attempt

Turbocaser Express™ 7” - Second Deployment Offshore Norway Delights Client on Challenging Run by Getting 7” Liner to TD at First Attempt

1 © 2012 Deep Casing Tools Turbocaser Express™ 7” - second deployment offshore Norway delights client on challenging run by getting 7” liner to TD at first attempt 7” tool reams 2194 ft (669 m) @ 141 ft (43 m) /hour, helps land production liner at TD, first time Objectives ?Run 7” liner in 9½” hole to TD @ 90 in unstable zones, at first attempt ?Have Turbocaser™ Express drill-thru available ?Cement as per program Well Background and