Tunnel lining replacement monitoring

Tunnel lining replacement monitoring

Pages 1 Pages

For information on FlatMesh – our award-winning wireless asset condition monitoring solution, call: 0207 731 8269 email: gsmith@senceive.com visit: senceive.com ©2015 Senceive Ltd. Hurlingham Studios, Ranelagh Gardens, London SW6 3PA CASE STUDY Tunnel lining replacement monitoring CLIENT: LONDON UNDERGROUND THE CHALLENGE A stretch of London Underground’s Jubilee line between Bond St and Baker St required the concrete lining to be replaced with cast steel (SGI) segments. This extremely ambitious project involved two special engineering trains replacing the lining shift by shift during engineering hours. Monitoring was required ahead of the works on temporary restraining rings, so needed to be flexible and easy to both deploy and re-deploy. Monitoring was also required immediat