Case Study

Transmission Line

Transmission Line

Pages 1 Pages

235061 Wrangler Link SE Calgary, AB T1X 0K3 T: 403-228-1767 F: 403-245-6632 E: info@cyntech.com www.cyntech.com Manitoba Hydro was constructing a new double circuit 230kV power transmission line in northern Manitoba. New towers needed to be erected, and the soil conditions required an innovative solution. Cyntech was able to provide foundations for these towers, at considerable savings over traditional methods. In all, Cyntech provided 1,0

Join for free to read