Case Study

Trafford College Refurbishment

Trafford College Refurbishment

Pages 4 Pages

Case Study – Trafford College Refurbishment Project Title Trafford College Sub Floor Decontamination Location Trafford College - Manchester Client Trafford College Joe D’Alessio (Project Manager - Arcadis UK (EC Harris)) Client Representative John Frowen (Health & Safety Manager – Trafford College) Project Value £525,000.00 Project Commencement June 2012 Project Completion February 2013 Project Description Decontamination of subfloor ducts (asbestos insulation debris). Challenges Works to be completed during a main campus refurbishment and with the college remaining fully operational at all times. Project Inception Winsulate had previously been employed as the Educational