Head Office, UK & Export Sales Compass Works, 410 Brightside Lane, Sheffield S9 2SP Tel: +44 (0) 114 2611126 • Fax: +44 (0) 114 2611165 • Email: enquiry@ekspan.co.uk Website: www.ekspan.com CASE STUDY Ekspan’s Workscope Works commenced with an initial survey and assessment of the current walkway floors to finalise the design and manufacture of the steel supporting structural frames to hold the glass panels. An underslung gantry was then installed to act as a working platform to undertake the works from. The existing oak flooring and substructure local to the final glass panel positions were carefully removed in various stages - starting with removal of 20mm thick oak boards, 18mm plywood boards, 45mm thick PIR insulation boards and rubber matting. The screed layers, after markin