Case Study
The Madison, London E14
Aadasd FERBOX units showing folded pull-out bars within offset casing. Our role As a trusted supplier to Morrisroe, Invisible Connections was selected to supply reinforcement continuity strip requirements for the 53 storey superstructure. During early stage construction, we were called upon to produce a bespoke Ferbox design to suit a capping beam to slab interface detail. Project description Rising to 187m, this Marsh Wall landmark is a slender hexagonal glass clad tower. The luxury residential development is adjacent to Canary Wharf in London, E14. Outcome We needed to devise a method of accommodating the extra long (1m) 16mm pull-out bars. This aspect was important to the design and could not be compromised. Manufacture using a traditi