THE ENERGY TO IMPROVE HOSPITALS

THE ENERGY TO IMPROVE HOSPITALS

Pages 2 Pages

THE ENERGY TO IMPROVE HOSPITALS WINDEMULLER Partners in your success windemuller.us OVERVIEW THE CHALLENGES The very nature of the project was a challenge. First, Windemuller had to fit the hospital’s main electrical distribution equipment into an existing mechanical room in the basement of the hospital. This mechanical room was located on the opposite side of the hospital campus from the existing electrical room. Second, once the new electrical room was set up, we had to cut over the hospital’s electrical loads from the old equipment to the new equipment. Perhaps most crucially, we had to execute all electrical cutovers without disrupting hospital operations. In a hospital setting, conducting a job like this isn’t a matter of minimizing downtime, but of eliminating it altogether. In o