The City of Baxter Minnesota Installs and Starts-Up an 800 Pound-Per-Day Microclor On-Site Hypochlorite System in Three Days

The City of Baxter Minnesota Installs and Starts-Up an 800 Pound-Per-Day Microclor On-Site Hypochlorite System in Three Days

www.ugsicorp.com PSI MC PP 1032 Baxter MN 07-18-2018 The City of Baxter Minnesota Installs and Starts -Up an 800 Pound -Per -Day Microclor® On -Site Hypochlorite System in Three Days The City of Baxter, located in central Minnesota, has always endeavored to deliver superior and reliable service to their customer base with a strong dose of self- reliance. Their 5 million gallon per day water plant is located near a middle school and the Baxter Public Utilities Water Department (Baxter) determined that the safety of on-site sodium hypochlorite generation for water disinfection made the most sense for the community. The utility is no stranger to complex water treatment processes as it deals with high iron, manganese and naturally occurring ammonia for their chlorinate