Case Study
Successful Switchgear Transplant for Standard Life Data Centre
Innovators in Protection Technology Location Works Load Status Site visit 1 Open, rack-out and remove ACB1 (Ellison) CS1 running on UPS for 15 minutes Site visit 1 Close bus-coupler CS1 fed by Tx 2, CS2 fed by Tx2 Factory Transplant TemPower 2 ACB into Ellison ACB1 shell