Standby Diesel Generators For London Skyscrapers

Standby Diesel Generators For London Skyscrapers

Pages 4 Pages

CASE STUDY 122 Leadenhall Street, London CLIENT: Crown House T echnologies COMMISSION: 4 x 2500KVA 11kV containerised standby diesel generators with bespoke control system COMMENCEMENT DATE: April 2012 COMPLETION DATE: May 2014 “The size of each item was restricted by the openings in the building’s superstructure. The permanent loadbank was also designed in three sections to suit site access restrictions.”CASE STUDY 122 Leadenhall Street,