Case Study
St Paul's Cathedral, London
Hamworthy provided a exible and e cient modular boiler and hot water solution to t the building and St Paul's cathedral has reduced its gas consumption by close to 40% compared to using the old boilers before the refurbishment. The cathedral’s existing heating system consisted of three steel shell boilers tted in the 1960s which received a burner upgrade in the 1980s. Problems on the equipment occurred and were xed until the boilers nally started leaking and could not be repaired anymore. At this point, Robin Bunton from Bunton M&E Services advised replacement boilers were necessary. Together with Mike Crouch, Hamworthy’s agent for the area, and Nick Coates from Blue Print Building Services Design, he worked on the speci cation for the cathedral’s heating and hot water refurbishment p