Case Study
Spray Paver with NAVITRONIC Plus® Makes its Norwegian Debut
Since the airport remained open to air traffic during the day, paving work could only be done between midnight and 6 am. Spray Paver with NAVITRONIC Plus® Makes its Norwegian Debut SUPER 1800-2 with SprayJet Module refurbishes Tromsø airport. Tromsø airport in northern Norway is a vital hub for numerous traffic links both within the country and to the neighbouring states. The runway’s wearing course needs renewing on a regular basis as it gets severely eroded by the constantly blowing, extremely salty wind coming in from the Arctic Sea. This time, in addition to pavement rehabilitation, the runway was also to be extended by 250m. Contractor Lemminkäinen Norge AS opted for a VÖGELESUPER 1800-2 with SprayJet Moduleto carry out the asphalt works. For the first time in Norway, the paver was eq