Case Study
SPIRA-COOL® Solution
A North American foundry customer had two existing parallel lines in their facility. The second line was to be modified and run a special alloy material. To compound this change, prior to having the sprue removed the alloys needed to be cooled before joining in with first line to be blasted. From A to B sounded impossible... atfirst! - GK engineers went to work studying the options for this customer. Due to a lack of space, the GK SPIRA-COOL® was the first considered. Able to replace the otherwise 122 feet of space needed for a regular vibratory conveyor, the SPIRA-COOL® could do so in 18 feet. It would also gain a large amount of the elevation needed to bring the alloys back to the first line.