Case Study
SorbWebTM Plus Secondary Oil Containment System
SorbWebTM Plus Secondary Oil Containment System Case Study Scope of Project This turnkey project was divided into phases. Each phase involved three main tasks: 1) SorbWebTM Plus system design and material procurement 2) Construction, including excavation, soil disposal and SorbWebTM Plus installation and 3) Environmental engineering, including soil sampling and testing. Kinectrics acted as the general contractor for the entire project. Work Performed Stones and soil were removed from around and behind the MOT units. In those areas where SorbWebTM would have been impractical, Kinectrics installed rebar with concrete slopes towards containment system areas. Additional excavation was performed using Gradall scraping, 6“ at a time. Pre-cast cement blocks formed the exterior and sides of th