Solving An Uphill Battle for Stratton Mountain Commercial Kitchen Flooring

Solving An Uphill Battle for Stratton Mountain Commercial Kitchen Flooring

case study Solving An Uphill Battle for Stratton Mountain Commercial Kitchen Flooring Project Overview Black Bear spent a week on the jobsite at the Stratton Moun - tain resort to value engineer a solution that would provide greater coverage and durability in two commercial kitchens. The existing flooring was difficult and costly to maintain. The Process STEP 1: Prep existing hardwood floors for urethane overlay STEP 2: Install Fiberglass Mesh Tape with 3/4 oz. per sq.ft. STEP 3: Waterproof with flexible epoxy membrane over wood at 4 inches off the walls STEP 4: Install Dur-A-Flex Elast-O-Coat STEP 5: Apply Poly-Crete MDB at 1/4 inch STEP 6: Use a ColorFast top coat with a 6 inch seamless cove Project Details Project Name – Stratton Mountain: 2 Commercial Kitchens Type of Busi