Case Study

Solar Farm Project Shutdown Prevented With Temporary Water Supply System

Solar Farm Project Shutdown Prevented With Temporary Water Supply System

Pages 1 Pages

Solar Farm Project Shutdown Prevented With Temporary Water Supply System PumPs • Tanks • FilTraTion • PiPe • sPillguards 800 742 7246 rainforrent.com BACKGROUND As plans for the installation of a 550 megawatt solar farm in Central California developed, it was identified that dust control would be crucial. As a result of the Environmental Impact Report, no dust could be in the air. Without continual dust control, the job would be shut down. OUTCOME A system of pump stations was designed by Rain for Rent to provide water for dust control to the solar power plant construction, allowing construction to continue uninterrupted. HIGHLIGHTS Rain for Rent provided several pump stations that pulled water from a pond and numerous wells which fed into several sets of tanks connected to J-sta

Join for free to read