Case Study
SMART Intervention Services Identified Lightweight Fish and Prevented Possible Work String Failure
Case History Baker Hughes SMART Intervention SM services were used for a high-risk deepwater Gulf of Mexico workover project. The objective was to remove a Baker Hughes retrievable high- pressure/high-temperature isolation packer set at ~26,254 ft (8002 m) measured depth (MD) to allow the operator to abandon the lower gravel-pack completion and recomplete just above the failed gravel-pack. The operator used the SENTIO ™ downhole data