WWW.AP-GROUP.CO.UK SINBAD REFURBISHMENT PROJECT REQUIREMENTS: STEEL REPAIRS, PIPE RENEWALS, GRIT-BLASTING THE HULL, ELECTRICAL REPAIRS AND INSTALLATIONS, MAIN ENGINE REPAIRS AND REFURBISHING THE ANCHORS. THE PROJECT: A&P Tyne, part of the A&P Group, successfully completed major refurbishment works and complete repaint to the 15,000 tonne, 183 metre long vessel. The project was in the Tyne yard’s dry dock for 14 days with the project compl