Shared Learning on M25 leads to step change in Joint Replacement

Shared Learning on M25 leads to step change in Joint Replacement

Pages 2 Pages

www.osborne.co.uk • 0800 0258 008 • enquiries@osborne.co.uk Contact: mike.o’connor@osborne.co.uk Shared Learning on M25 leads to step change in Joint Replacement PROJECT M25 Gade Valley Viaduct Joint Replacement CUSTOMER Connect Plus Services LOCATION King’s Langley/ M25 J20 www.osborne.co.uk • 0800 0258 008 • enquiries@osborne.co.uk Contact: mike.o’connor@osborne.co.uk Issue Large motorway bridge decks expand and contract with changes in temperature. Mechanical movement joints extend across the lanes to enable this to happen. During the life of the bridge these multi-element joints wear and have to be replaced. Replacing the joints using traditional methods requires lanes to be closed for several days or even weeks. This can be extremely disr