Selby Leisure Complex

Selby Leisure Complex

Selby Leisure Complex Foundation piling has been completed by Aarsleff for the new £6m leisure complex at Selby, North Yorkshire. Two hundred and thirty eight precast concrete piles were driven up to 20 metres for the new Abbey Leisure Centre that replaces the complex destroyed by fire in 2012. Utilising square section sizes of 200mm and 250mm class D jointed piles ranging in length from 16 to 17 metres the piles were driven to found o