Case Study
Sakhalin Energy operates the world’s largest oil and gas development and used AVEVA to streamline its contract management process.
Sakhalin Energy operates the world’s largest oil and gas development and used AVEVA to streamline its contract management process.
Goals y To implement a database that allowed for full transparency. y To mitigate contractual risk. y To fully comply with anti-bribery and corruption rules. Challenges y An outdated contract management system made contracts confusing. y Due to being in the early stages of two major expansion projects, time was tight. AVEVA Solution y AVEVA ProCon Results y Sakhalin Energy used AVEVA ProCon on the Sakhalin 2 project. Shareholders on the project were Gazprom, Shell, Mitsui, and Mitsubishi. y Over 1,000 contracts are now streamlined and accounted for. y Growth is now closely watched. y All contracting and procurement process are conveniently systemised and codified. Sakhalin Energy Investment Company Ltd. INDUSTRY Owner Operator Sakhalin Energy, based in the Russian Feder