06 CASE STUDY 03 Triveni Turbines shipped the whole turbine to its factory in Bangalore where the Triveni Refurbishing team rebuilt the whole turbine through reverse engineering. There was a need to manufacture new blades through reverse engineering and it was found that the old design (root blades) was no longer useable. The entire project was completed within 4 months. The turbine is on full power for over 3 years now with no issues since and we have yet another satisfied customer. Restoration of Turbine INTRODUCTION The customer is a reputed group in the palm oil segment from Malaysia. The turbine in operation was completely damaged and the rotor shaft was sheared off. SOLUTION CHALLENGE The challenge was to rebuild the complete turbine without existing drawings and replace the br